Planning guide · updated November 2026
Campbell sits in the heart of the South Bay between San Jose, Los Gatos and Cupertino. A lot of the custom building here is replacement: an older ranch or mid-century house comes down and a new single-family home goes up on the same lot. Below is how we plan new homes in Campbell so the zoning path, the trees, any historic listing and the construction schedule are understood before the drawings are locked.
Harrod Built takes on new custom homes and whole-home rebuilds in the South Bay and on the Peninsula, including Campbell. Have a Campbell lot, a tear-down or a plan set ready for an estimate? Phone 805-712-8993 or use the form at the bottom of this page.

The short answer
In the City of Campbell, a new single-family house on an R-1 lot is usually submitted directly to the Building Inspection Division for a building permit through the MGO online portal, without a prior Planning land use permit. Planning still reviews tree removal, historic resource work, variances and Site and Architectural Review when those apply. Heavy rebuilds that keep pieces of the original house may be classified as a new dwelling using portions of the original structure and have to meet new-house standards. Santa Clara County Fire reviews new construction. (we confirm per lot)
1. Who reviews what
A city with Building, Planning and County Fire
Campbell’s Community Development page houses the Building Division page and the Planning Division page. The Building Division approves plans and issues permits for construction in the city; other agencies handle the rest:
| Agency or office | Its part in a new Campbell house |
|---|---|
| Building Inspection Division | Plan review, building permits and field inspections for new construction, through the MGO online portal; New House Determinations when a heavy rebuild keeps pieces of the original house. |
| Planning Division | Zoning checks, tree removal permits, historic resource work, variances and Site and Architectural Review when those permits apply; most R-1 new houses go straight to Building. |
| Planning Commission | Public hearings on land-use applications such as Conditional Use Permits, Site and Architectural Review Permits, Planned Development Permits and subdivisions. |
| Historic Preservation Board | Advisory review when a property is on the Historic Resource Inventory or when historic rules apply. |
| Public Works / Engineering | Frontage improvements, grading and site improvement permits, stormwater and right-of-way work that ride with a new house. |
| Santa Clara County Fire Department | Fire plan review for new construction, including fire sprinkler systems where required. |
| West Valley Sanitation District | Sewer connection and sanitation permits for new dwellings in its service area. |
Summarized from City of Campbell Building, Planning, Historic Preservation, Planning Commission and handout pages and from Santa Clara County Fire, read November 5, 2026.
We confirm the zoning district and pull the City’s records for the lot before anything else. Our Los Gatos and South Bay custom home page describes the kind of homes we take on in the South Bay; next door, our Cupertino and Saratoga permit guide cover neighboring cities with their own review boards. (we confirm per lot)
2. Zoning and the R-1 path
Why most Campbell new houses go straight to Building
The City’s Zoning and Land Use page points to the interactive GIS viewer and the Campbell Zoning Code (Title 21). The City Maps Gallery and the Campbell interactive GIS viewer are the usual places to confirm land use and zoning. The 2040 General Plan sets the long-range land-use policy behind those maps.
On the Planning side, the Single-Family Residential application checklist explains that proposals for new single-family dwellings on properties in the R-1 (Single-Family Residential) zoning district no longer need prior approval of a land use permit from Planning. Those projects submit directly to Building for a building permit, using the new single-family guide on the Building Application Guides page.
Planning review still applies when the lot is historic, when a variance is needed, when Site and Architectural Review is required, or when the property is not in the R-1 district. Recorded easements in a title report can widen setbacks beyond the ordinance, so we read title before drawing the footprint.
The Planning Counter Service page handles brief zoning questions; deeper lot research is done in writing. (we confirm per lot)
3. New house vs keeping pieces
The City’s New House Determination
Not every Campbell tear-down is a clean slab. When a heavy rebuild keeps pieces of the original house, the City may classify the work as a new dwelling using portions of the original structure. Crossing the City’s thresholds for how much of the existing house comes out triggers a New House Determination from the Building Inspection Division before a building permit is filed in MGO.
Once classified as new, the project has to meet the standards that apply to a new house — current zoning, fire sprinklers where required, frontage improvements, water-efficient landscape rules and reach-code items. Keeping a lawfully built wall that sits inside today’s setbacks can be allowed under the City’s nonconforming-structure rules when that wall is not structurally altered; we confirm that reading with Building on the specific plan.
Handouts explaining the New House path sit on the Building Handouts and Forms page. We run the determination early when any of the original house might stay, because the classification changes the code path, the fire and frontage scope and the schedule.
4. Historic listings and trees
When Planning still comes first
The City’s Historic Preservation page explains that Campbell keeps a Historic Resource Inventory of buildings, structures and districts, plus a list of properties that may be eligible. Work on a listed historic property uses the Historic Resource Alteration Permit path and may go through the Historic Preservation Board page. Historic design guidelines and the Secretary of the Interior’s treatment standards guide that review.
Trees are their own track. The Tree Protection Ordinance protects listed species above a trunk-size threshold on single-family lots — including oak, redwood, cedar and ash — and Heritage trees have their own list under the historic regulations. Removing a protected tree needs a Tree Removal Permit through Planning; the Planning Applications page and the Planning Handouts page carry the checklists and the tree protection handout. Construction cannot run inside the dripline of a protected tree without the City’s protection measures in place.
We bring an arborist in before the footprint is set, and we check the Historic Resource Inventory before design starts. (we confirm per lot)
5. The building submittal
What Building wants for a new house
Since May 4, 2020, all building permit applications go through the City’s MyGovernmentOnline portal. The MGO Application Center is where you create an account; the Building Application Guides page organize applications by type, including new single-family residential construction. Plans and supporting documents are uploaded as separate named files:
- Construction plans. Architectural, structural and related sheets prepared to the City’s naming rules.
- Soils report. The geotechnical report that the foundation and drainage design follow.
- Structural and energy calculations. The engineering and Title 24 documents for plan review.
- CALGreen and waste tracking. Green building items and a waste management plan monitored through Green Halo.
- Clean Bay sheet. The Blueprint for a Clean Bay stormwater practices sheet in the plan set.
- Demolition clearance. Demolition clearance and PCB screening forms before the old house comes down; forms live on the Building Handouts page.
A separate Grading and Site Improvement Permit covers grading, paved surfaces, utilities, stormwater and landscaping; the building permit for a new dwelling is not issued until that grading permit is also issued. Concurrent review is normal. Forms, the Construction Management Plan template and jobsite signage for new residential work are on the Building Handouts and Forms page. Owner-builder questions are covered in our owner-builder comparison.
6. Fire, air quality and energy
County Fire, the Air Quality Ordinance and reach codes
Campbell is served by the Santa Clara County Fire Department, which reviews plans for new construction; its fire prevention page covers fire prevention. Fire sprinkler review is a separate County Fire track that has to clear before the City finishes its own review.
- Air Quality Ordinance. The City adopted an Air Quality Ordinance that prohibits NOx emissions from appliances and equipment in new residential buildings and substantial rebuilds that use parts of existing buildings. The Electrify Your Home page explains the policy and points to Silicon Valley Clean Energy and Bay Area air-district rules.
- Reach codes and electrification. Reach-code and building-code handouts on the Building Handouts page set local energy and electrification requirements for new homes on top of the state Energy Code.
- State Energy Code. The state’s 2025 Energy Code applies to permit applications filed on or after January 1, 2026, and our Title 24 overview explains the energy side of a new house.
- Fire hazard maps. Check the address on the State Fire Marshal’s fire hazard severity zone maps as well; our fire hazard severity zone guide explains what a mapped lot means.
(we confirm per lot)
7. Construction in Campbell
Hours, inspections, frontage and licenses
The City’s construction-hours rules, summarized on the inspections page and the construction-hours flyer, shape when site work can run: weekdays and Saturdays are open under the posted window; Sundays and state and federal holidays are closed for site work unless an exception is granted.
- Construction Management Plan. A plan meeting CalGreen and local code has to appear on the cover sheet; non-compliance can stop an inspection.
- Jobsite signage. New residential projects post the City’s fillable jobsite signage.
- Inspections. Field inspections are scheduled through MGO or by phone; the inspections page explains windows and the sequence of inspections.
- Frontage improvements. A new single-family dwelling typically triggers Public Works frontage work such as curb, gutter, sidewalk, driveway and street trees; Engineering confirms the scope per lot.
- Business license. The contractor keeps a current City business license and a CSLB license in good standing for the life of the job.
Active permits in the neighborhood show on the Permit Center Map. We build the schedule around the City’s hours and inspection process so heavy site work lands when it is allowed.
8. Order of steps
How we usually sequence a Campbell new home
| Stage | What happens | What usually sets the pace |
|---|---|---|
| Lot research | Survey, R-1 or other zoning, title easements, protected trees, Historic Resource Inventory status, fire agency and utilities. | Surveyor, title, arborist and City records. |
| Concept and New House path | A full new house or a rebuild that keeps pieces of the original, checked against zoning and the City’s New House Determination rules when they apply. | How much of the existing house stays. |
| Planning permits when they apply | Tree removal, historic resource work, a variance or Site and Architectural Review when the lot needs them; otherwise R-1 new houses go to Building. | Hearing calendars when a Commission review is required. |
| Demolition clearance | Demolition clearance, PCB screening and waste tracking before the old house comes down. | Utility disconnects and clearance forms. |
| Building and fire plan review | MGO submittal of drawings, soils report, structural and energy calculations, CALGreen items and County Fire review; grading and site improvement permit alongside. | Correction rounds and consultant turnaround. |
| Construction | Construction management plan, jobsite signage, inspections, construction-hours rules and frontage work. | Inspection scheduling and weather. |
A common sequence for a new house or a full rebuild in Campbell; a historic listing, a tree removal or a non-R-1 zoning district can each change it.
Our custom home timeline guide puts design, approvals and construction on one calendar. Neighboring cities handle new houses differently; our guides for Cupertino, Saratoga, Los Gatos, Monte Sereno, Los Altos, Los Altos Hills, Palo Alto, Menlo Park, Atherton, Woodside and Portola Valley and Burlingame cover their rules.
9. Before you design
Questions to answer about your Campbell lot
- Is the lot inside the City of Campbell, and is there a current boundary and topographic survey?
- Is it zoned R-1, or does another district change the Planning path?
- Do recorded easements on title change the setbacks?
- Is a full new home the cleaner path than trying to keep pieces of the existing house, and does a New House Determination apply?
- Is the property on the Historic Resource Inventory or otherwise historic?
- Which trees on or near the lot are protected, and which need a removal permit or a protection plan?
- What frontage improvements will Public Works require with a new dwelling?
- Which fire agency and sanitation district serve the address?
Owners who already have an architect send us the drawings and we estimate and build from them; owners starting fresh can have Harrod Drafting & Design, our sister studio, draw the house and the permit set.
How we help
What Harrod Built brings to a Campbell new home
Harrod Built (CSLB #986950) is a family-run general contractor building on the Peninsula, in the South Bay and on the Central Coast. On a new home or a full rebuild in Campbell, our role usually covers:
- Lot review first. Zoning district, title easements, trees, historic status, fire agency and the New House path, checked before we write an estimate.
- Estimates during design. We estimate while the design is still flexible, including the cost of keeping or removing pieces of an existing house.
- Demolition lined up early. Utility disconnects, demolition clearance, PCB screening, waste tracking and tree protection set before the tear-down date.
- Site work from real plans. Soils recommendations, foundation, drainage, grading permit and frontage work taken from the engineered set, not allowances.
- Run to the City’s rules. Construction Management Plan, hours, inspections and a schedule that respects neighbor noticing when Planning is involved.
- Design support. Harrod Drafting & Design can draw the house and the permit set, or we build from your architect’s plans.
- Landscape. Paso Robles Landscaping, our landscape company, handles planting, irrigation and hardscape to the approved landscape plan.
Before hiring any builder, look up the license on the state license lookup; the CSLB’s advice on hiring a contractor and our article on how to check a CSLB license explain what to look for. Nearby we also build in Los Gatos, Saratoga, Palo Alto, Atherton and Woodside and Portola Valley, and farther south in Monterey, San Luis Obispo and Santa Barbara counties, through general contracting or design-build. Our process page walks through the steps from estimate to move-in, and our contract type comparison explains fixed-sum and cost-plus agreements. For the local market, see our page on custom homes in Los Gatos and nearby South Bay towns.
Pricing a new home or a full rebuild in Campbell? Send the address and any drawings you have. We check the zoning district, the New House path, protected trees, any historic listing, the fire agency and the submittal package, then send back a written estimate. Phone 805-712-8993 or reach us here.
Sources: City of Campbell Building Division, Building Application Guides, Building Handouts and Forms, inspections, Electrify Your Home, Community Development, Planning Division, Planning Applications, Planning Handouts, Zoning and Land Use, Planning Commission, Historic Preservation and Historic Preservation Board pages; the City Maps Gallery, interactive GIS viewer, Permit Center Map, MGO Application Center and the Zoning Code (Title 21) via Municode; Building and Planning application guides and handouts for new single-family construction, New House Determination, tree protection, tree removal, demolition clearance, reach codes and the Construction Management Plan. Fire sources: Santa Clara County Fire Department home and fire prevention pages. State sources: the CEC’s 2025 energy standards and the CSLB, all reviewed November 5, 2026. This page is a general overview, not legal or code advice; what applies to a given lot is decided by the City of Campbell and the other agencies involved.
Who issues building permits in Campbell?
The City of Campbell Building Inspection Division, through electronic submittal on the MGO portal. Planning reviews first when a tree removal, historic, variance or Site and Architectural Review permit is needed, and Santa Clara County Fire reviews new construction.
Does a new R-1 house in Campbell need a Planning land use permit?
Usually not. The City’s Single-Family Residential checklist says new single-family dwellings on R-1 lots no longer need prior Planning land use approval and can go directly to Building for a building permit.
What is a New House Determination in Campbell?
A Building Inspection Division review used when a heavy rebuild keeps pieces of the original house. If the City classifies the work as a new dwelling using portions of the original structure, the project has to meet new-house standards for zoning, fire, frontage, landscape water rules and reach codes.
Which trees are protected in Campbell?
Listed species above a trunk-size threshold on single-family lots — including oak, redwood, cedar and ash — plus Heritage trees. Removing a protected tree needs a Tree Removal Permit, and trees must be protected during construction.
What extra rules apply on a historic Campbell lot?
Properties on the Historic Resource Inventory use the Historic Resource Alteration Permit path and may go through the Historic Preservation Board, following the City’s historic design guidelines and the Secretary of the Interior’s standards.
Which fire department reviews a Campbell new home?
Santa Clara County Fire Department. Fire sprinkler review is a separate County Fire track that has to clear alongside the City’s building plan review.
Planning guides
Budget and planning guides
Building a new home in Cupertino
R1 zoning, one-story and two-story paths, consulting-architect review, hillside rules and County Fire.
Building or remodeling in Los Gatos
Architecture and Site review, hillside standards and story poles in the South Bay.
Building or remodeling in Saratoga
Design review, hillside rules, protected trees and the City permit path next door.
Building a new home in Monte Sereno
Site and architecture review, hillside lots, trees and the fire district in the South Bay hills.
Building or remodeling in Los Altos
Design review, the Zoning Administrator, daylight plane, protected trees and the City permit path.
Building a new home in Los Altos Hills
Site development review, Fast Track, floor area by slope, story poles, oaks and the Town permit path.
Building or remodeling in Palo Alto
Individual Review for two-story homes, protected trees, flood zones, basements and deconstruction.
How long a custom home takes
Design, approvals, permits and construction laid end to end.
Building a new home in Sunnyvale
Design Review levels, Eichler and heritage guidelines, protected trees and the City’s own fire review.
Building a new home in Almaden
Single-Family House Permit, hillsides, ordinance-size trees, WUI fire rules and the City of San José permit path.
Start your project
Planning a new home in Campbell? Tell us about your property.