Building a New Home in Burlingame: Design Review, Hillside Rules and the City Permit Path

Planning guide · updated November 2026

Burlingame is a Peninsula city between the Bay and the hills, next to Hillsborough and Millbrae. Its Neighborhood Design Guidebook was written to keep new houses compatible with the character of established streets, and every new house goes to the Planning Commission for design review before the Building Division will take a Residential New submittal. Much of the custom building we see here is replacement: an older house comes down and a new one is designed for the same lot. Below is how we plan new homes in Burlingame so the design, the site and the construction schedule are understood before the drawings are locked.

Harrod Built takes on new custom homes and whole-home rebuilds on the Peninsula and in the South Bay, including Burlingame. Have a Burlingame lot, a tear-down or a plan set ready for an estimate? Phone 805-712-8993 or use the form at the bottom of this page.

Pool at dusk reflecting the lit rear elevation of a Modern French Country custom home, Templeton
Pictured: a Modern French Country home we built in Templeton, shown for craft and finish; this is not a Burlingame project. In Burlingame, the neighborhood around the lot, the trees, any hillside overlay and the City’s Planning Commission design review shape a new house long before a building permit is filed.

The short answer

In the City of Burlingame, a new house needs residential design review from the Planning Commission, judged against the Neighborhood Design Guidebook and the R-1 zoning standards, before the Building Division accepts a Residential New building permit through eTRAKiT. Lots in the Hillside Overlay Zone also need a hillside area construction permit with neighbor notice. Taking down the old house needs its own demolition path with an air district job number, PG&E release, City water and sewer disconnects and a recycling plan. Central County Fire reviews new construction for fire and life safety, and the City applies its reach codes to new single-family projects. (we confirm per lot)

1. Who reviews what

A city with Planning, Building and Central County Fire

Burlingame’s Community Development Department houses Planning and Building, according to its Community Development page, and works with other agencies for the rest:

Agency or officeIts part in a new Burlingame house
Planning DivisionZoning checks, residential design review for the Planning Commission, hillside area construction permits, historic review where it applies, and the files that go with a design review hearing.
Planning CommissionA public hearing body that reviews new houses and other design review projects against the Neighborhood Design Guidebook, the zoning standards and neighborhood character.
Building DivisionPlan check, building and demolition permits and inspections, through the City’s eTRAKiT portal and the Building counter.
Public Works / EngineeringEncroachment permits for work in the street, water and sewer disconnect sign-offs before demolition, and related frontage work.
Central County Fire DepartmentFire and life-safety plan review for new construction, fire construction permits, and wildland-urban interface guidance for mapped lots in Burlingame.
Bay Area Air District and PG&EThe air district’s job number for demolition and PG&E’s written confirmation that gas and electric are disconnected before a house comes down.

Summarized from City of Burlingame Community Development, Building, Planning and permits pages and from Central County Fire, read November 5, 2026.

The Building Division page accepts new building submittals once Planning Commission approval is in hand, or when a project does not need that approval. We confirm the city limits and pull the City’s records for the lot before anything else. Our Atherton and Peninsula custom home page describes the kind of homes we take on nearby. Next door, our Hillsborough permit guide covers Hillsborough’s Architecture and Design Review Board under the same fire department. (we confirm per lot)

2. Residential design review

Planning Commission review of a new house

The City’s residential design review page states that all new houses built in Burlingame require an application to the Planning Commission for design review. Projects are checked against the Neighborhood Design Guidebook, which guides design based on the style of the existing house and the character of the surrounding neighborhood, and against the R-1 zoning district regulations for setbacks, lot coverage, building height and floor area. Parking rules are reviewed at the same time.

The residential design review submittal requirements list what a design review package needs before a hearing can be scheduled: a signed project application form, floor plans of existing and proposed layouts, elevations and sections of every side, a site plan, a landscape plan for new construction, materials notes and related sheets. Incomplete or hard-to-read files are not accepted. We design to the Guidebook and the zoning envelope from the first concept, because a late redesign costs a commission cycle.

3. Neighborhood Design Guidebook and zoning

What “compatible” means on a Burlingame street

The design guidelines page point to the Neighborhood Design Guidebook as the reference for residential design review. The Guidebook, prepared by a Planning Commission subcommittee, is meant to keep new work informative about neighborhood character rather than forcing a single style. In practice we read:

  • Street character. How the house faces the street, the rhythm of porches and entries nearby, and whether the mass reads as one house or as a stack of floors.
  • Roof and wall forms. Roof pitch and plate heights that fit the block, with wall planes broken up so a new house does not dominate its neighbors.
  • Materials. Exterior materials and colors that relate to the houses around the lot, called out on the elevations.
  • Landscape. Planting that joins the house to the ground and softens taller walls; the City’s private-property tree list lists trees that grow well on private lots and notes that smaller trees suit hillside plantings where views matter.
  • The measurable envelope. The zoning code and maps page carries the R-1 development standards for setbacks, coverage, height and floor area that the design review package has to meet.

Where a lot may be historic, the historic preservation page explains the City’s preservation path; we check that early so a survey or review is not a surprise mid-design. (we confirm per lot)

4. Hillside overlay

When a hillside area construction permit applies

Lots inside the Hillside Overlay Zone follow Code section 25.20.040. The City’s hillside area construction permit procedures explain that the permit is required for all new residences, new accessory structures, or changes in roof elevations on existing houses in that overlay, so neighbors can review work that could affect distant views from inside nearby homes. Fences that already meet code are outside the permit.

The review starts with an application, site plan, floor plan and elevations. Notice and plans go to nearby owners for a short review window. If nobody calls the project up for a Planning Commission hearing in that window, the permit is approved and a building permit application can follow. If it is called up, it goes to a public hearing.

The hillside area construction permit application and the hillside overlay map on the City’s other residential reviews page page are the starting points. We check the overlay on day one, because a hillside path changes both the notice schedule and how the roof and massing are judged. (we confirm per lot)

5. Taking down the old house

The demolition path before a rebuild

On the online permitting portal and submittal instructions, demolition of a single-family house is filed as a Residential Demo permit. The demolition supplemental permit application lists what has to be in hand before the City will issue it:

  • Air district job number. A demolition permit from the Bay Area Air District, with the job number and a copy of that permit in the City file.
  • PG&E release. A written letter confirming electric and gas service have been disconnected.
  • City water and sewer disconnects. Sign-offs from City departments, which first need an encroachment permit from Public Works.
  • Recycling plan. A construction and demolition recycling plan reviewed before demolition, as the City’s construction and demolition recycling requirements explain.
  • One permit per structure. Each building on the parcel that is coming down needs its own demolition permit for census reporting.

Demolition is often tied to the main building permit, though a standalone demolition permit can be issued in some cases at the Building Official’s discretion. We line up the air district number, the utility letters and the City disconnects early, because they often take longer than the tear-down itself.

6. Soils, grading and the building submittal

What Building wants for a new house

Once design review is approved, the building permit is filed as Residential New through the eTRAKiT online permit portal, with drawings uploaded under the City’s naming rules, as the online permitting portal and submittal instructions explains. The building permit submittal guide ask for a signed permit application, construction drawings and the supporting documents that apply:

  • Soils report. The soils report guidelines require a geotechnical soils report for all new residential buildings, and for hillside conditions, deep foundations and pier-and-grade-beam work. The civil and structural design has to follow the report.
  • Structural and energy. Calculations, Title 24 documentation and the sheets needed for plan check under the City’s current building safety design criteria.
  • Plan routing. Building routes the set to Planning, Engineering and the other departments that have to sign off before the permit is issued.
  • After approval. Remaining items such as the recycling plan, stormwater paperwork, encroachment permits and special inspection forms are finished before issuance, and the permit card and plans stay on site for inspections.

More forms live on the forms and documents page and City permits page pages, including the special inspection agreement. Owner-builder questions are covered in our owner-builder comparison.

7. Fire, wildfire and energy

Central County Fire and the City reach codes

Burlingame is served by the Central County Fire Department, which also covers Hillsborough and Millbrae, as the about Central County Fire explains. The Fire Prevention Division page provides fire and life-safety plan review for new building construction, fire suppression and fire alarm systems, plus construction inspections. Construction-related fire permits are summarized on the construction permits page.

  • Mapped fire hazard zones. The wildland-urban interface page explains that new Local Responsibility Area maps from the State Fire Marshal identify hazard severity zones inside Burlingame. Check the address on the State Fire Marshal’s fire hazard severity zone maps as well; a mapped lot brings in wildfire construction and defensible-space expectations, which our fire hazard severity zone guide explains.
  • Home hardening and vegetation. Central County Fire publishes defensible-space and home-hardening guidance for wildland-urban interface lots; we treat those as design inputs, not finish-out extras.
  • City reach codes. The reach codes page explains that Burlingame amended its reach code for new construction after a federal court decision on natural-gas bans. New single-family projects filed in the current window must beat the state energy design score by a set margin, with published exceptions; the single-family reach code checklist is the checklist Building uses. Multi-family and non-residential projects have their own source-energy margins.

The state’s 2025 Energy Code applies to permit applications filed on or after January 1, 2026, and our Title 24 overview explains the energy side of a new house. (we confirm per lot)

8. Construction in Burlingame

Hours, inspections and licenses

The Municipal Code limits when construction, demolition and grading can run, as the City’s construction hours flyer and codes and regulations page explain:

  • Hours. Work is allowed on weekdays and Saturdays within set hours, with shorter hours on Saturdays, and not on Sundays or the holidays listed in the Municipal Code, except with written approval from the Building Official for narrow public-safety or integrity reasons.
  • Inside work. Work entirely inside a closed building that stays within exterior ambient noise limits is treated differently under the noise rules.
  • Right-of-way work. Public Works work in the street follows its own weekday daytime window.
  • Inspections. The Building Division page explains that inspections are requested by phone or email once the permit is active, with the approved plans and permit card on site.
  • Business licenses. Contractors need an active California contractor license and a City business license before a permit is issued, as the building permit submittal guide and business license page explain.

We build the schedule around the City’s hours and inspection process so noisy site work lands when it is allowed.

9. Order of steps

How we usually sequence a Burlingame new home

StageWhat happensWhat usually sets the pace
Lot researchSurvey, zoning district, hillside overlay, trees, historic status, sewer and water, and the fire hazard map.Surveyor and arborist calendars.
Concept and design reviewA concept checked against the Neighborhood Design Guidebook and R-1 standards, then a residential design review package for the Planning Commission.Completeness review and the commission calendar.
Hillside path when it appliesA hillside area construction permit with neighbor notice when the lot sits in the Hillside Overlay Zone.Neighbor notice window and any call-up to a hearing.
Building and fire plan checkResidential New submittal through eTRAKiT, soils report, structural and energy documents, and Central County Fire review.Correction rounds and consultant turnaround.
Demolition of the old houseAir district job number, PG&E release, City water and sewer disconnects with an encroachment permit, and the recycling plan.Utility and City scheduling.
Construction and finalInspections, posted construction hours, special inspections and the final routing paperwork.Construction, weather and inspection scheduling.

A common sequence for a new house or a full rebuild in Burlingame; a hillside lot, a historic resource or a variance can each change it.

Our custom home timeline guide puts design, approvals and construction on one calendar. Neighboring cities and towns handle new houses differently; our guides for Hillsborough, Menlo Park, Atherton, Woodside and Portola Valley, Palo Alto, Los Altos, Los Altos Hills, Los Gatos and Saratoga cover their rules. Hillsborough shares Central County Fire with Burlingame, so the fire review language is similar even though the design review boards are not.

10. Before you design

Questions to answer about your Burlingame lot

  1. Is the lot inside the City of Burlingame, and is there a current boundary and topographic survey?
  2. Which zoning district is it in, and what do the R-1 standards allow for coverage, floor area, height and setbacks?
  3. Is the lot in the Hillside Overlay Zone, and would a new roof or house trigger the hillside area construction permit?
  4. What do the neighboring houses look like under the Neighborhood Design Guidebook?
  5. Which trees are on or near the lot, and will any protected tree need its own removal permit?
  6. Is the house a potential historic resource under the City’s preservation rules?
  7. Is the address in a mapped fire hazard zone, and will Central County Fire have notes on access, sprinklers or vegetation?
  8. Is a full new home the cleaner path than trying to keep pieces of the existing house?

Owners who already have an architect send us the drawings and we estimate and build from them; owners starting fresh can have Harrod Drafting & Design, our sister studio, draw the house and the permit set.

How we help

What Harrod Built brings to a Burlingame new home

Harrod Built (CSLB #986950) is a family-run general contractor building on the Peninsula, in the South Bay and on the Central Coast. On a new home or a full rebuild in Burlingame, our role usually covers:

  • Lot review first. City limits, zoning, hillside overlay, trees, historic status, sewer, fire zone and design review path, checked before we write an estimate.
  • Estimates during design. We estimate from the design review set, so the house the Planning Commission approves is one the owner is ready to build.
  • Demolition lined up early. Air district number, PG&E release, City water and sewer disconnects and the recycling plan started before the tear-down date.
  • Site work from real plans. Soils recommendations, foundation, drainage and frontage work taken from the engineered set, not allowances.
  • Run to the City’s rules. Posted hours, eTRAKiT inspections, business licenses for every trade and a schedule that respects neighbor notice windows.
  • Design support. Harrod Drafting & Design can draw the house and the permit set, or we build from your architect’s plans.
  • Landscape. Paso Robles Landscaping, our landscape company, handles planting, irrigation and hardscape to the approved landscape plan.

Before hiring any builder, look up the license on the state license lookup; the CSLB’s advice on hiring a contractor and our article on how to check a CSLB license explain what to look for. Nearby we also build in Atherton, Woodside and Portola Valley, Palo Alto, Los Gatos and Saratoga, and farther south in Monterey, San Luis Obispo and Santa Barbara counties, through general contracting or design-build. Our process page walks through the steps from estimate to move-in, and our contract type comparison explains fixed-sum and cost-plus agreements. For the local market, see our page on custom homes in Atherton and the nearby Peninsula towns.

Pricing a new home or a full rebuild in Burlingame? Send the address and any drawings you have. We check the zoning district and any hillside overlay, the design review path, the trees, the demolition and utility steps, the soils report, Central County Fire review and the City’s construction hours, then send back a written estimate. Phone 805-712-8993 or reach us here.

Sources: City of Burlingame Community Development, Building Division, Planning Division, residential design review, other residential reviews, Planning Commission, zoning, historic preservation, design guidelines, reach codes, codes and regulations, business license, permits, forms and documents and online permitting portal pages; the eTRAKiT portal; and the City’s building permit submittal guide, residential design review submittal requirements, project application form, minor design review procedures, hillside area construction permit procedures and application, demolition supplemental application, construction and demolition recycling requirements, single-family reach code checklist, soils report guidelines, building safety design criteria, construction hours flyer, Neighborhood Design Guidebook and private-property tree list. Fire sources: Central County Fire Department home, about, Fire Prevention, wildland-urban interface and construction permits pages. State sources: OSFM fire hazard severity zone maps, the CEC’s 2025 energy standards and the CSLB, all reviewed November 5, 2026. This page is a general overview, not legal or code advice; what applies to a given lot is decided by the City of Burlingame and the other agencies involved.

FAQ

Common questions

Something else on your mind? Call Michael at 805.712.8993.

Who issues building permits in Burlingame?

The City of Burlingame Building Division, through the eTRAKiT online permit portal. For a new house, the Planning Commission first approves residential design review, and Central County Fire reviews the construction documents for fire and life safety.

Does a new house in Burlingame need design review?

Yes. The City states that all new houses need an application to the Planning Commission for design review, checked against the Neighborhood Design Guidebook and the R-1 zoning standards for setbacks, coverage, height and floor area.

What is the hillside area construction permit?

A review required for new residences and certain roof changes on lots inside the Hillside Overlay Zone, so neighbors can weigh effects on distant views. Notice goes to nearby owners; if it is not called up for a hearing, the permit can be approved at staff level.

What does Burlingame need before an old house is demolished?

A Residential Demo permit with a Bay Area Air District job number, a PG&E letter confirming gas and electric are disconnected, City water and sewer disconnect sign-offs under an encroachment permit, and an approved construction and demolition recycling plan.

Does Burlingame require a soils report for a new house?

Yes. The Building Division’s soils report guidelines require a geotechnical report for new residential buildings, and for hillside conditions and certain deep or pier foundations. The structural design has to follow the report.

Which fire department reviews a Burlingame new home?

Central County Fire Department, which serves Burlingame, Hillsborough and Millbrae. Its Fire Prevention Division reviews new construction for fire and life safety and publishes wildland-urban interface guidance for mapped lots.

Start your project

Planning a new home in Burlingame? Tell us about your property.

A few details help us call you back with useful answers about budget, schedule and permits.

805.712.8993

michael@harrodbuilt.com
1345 Riverside Ave, Paso Robles, CA 93446
CSLB License #986950

    Prefer to talk? Call 805-712-8993.