Building or Remodeling in Atherton: Heritage Trees, Zoning Rules and the Town Permit Path

Planning guide · updated November 2026

Atherton is an all-residential town of large, heavily treed lots, with no commercial districts and two residential zones. Much of the building here is new custom homes on teardown lots and large remodels of existing estates. The Town doesn’t run a separate design review board for a single-family home that meets the code, but its zoning standards, its heritage tree ordinance and its construction rules are detailed, and they shape the plan from the first site visit. Below is the sequence we plan around on new homes, rebuilds, additions and large remodels in Town, so the drawings and the calendar account for it before anyone commits to a footprint.

Harrod Built builds custom homes, estate rebuilds, additions and major remodels across the Peninsula, and Atherton is one of the towns we cover. Want a second opinion on an Atherton property or plan set? Phone 805-712-8993 or send the details through the form below.

Overhead view of a tile-roof home with a pool, covered patios, a pergola and mature trees, Paso Robles
Pictured: an overhead view of a Tuscan Revival home we built in Paso Robles, shown for craft and site planning; this is not an Atherton project. On an Atherton estate lot, the same view is how the Town looks at a plan: where the house, pool, driveway and utilities sit relative to the setbacks and to every heritage tree on and near the site.

The short answer

The Town of Atherton issues building permits through its Building Department and ePlan submittal portal. The zoning check is a staff-level zoning clearance done by the town planner inside the building permit, so a house that meets the R-1A or R-1B standards usually needs no separate planning hearing. A special structures permit or variance from the Planning Commission comes in for taller homes in R-1A, certain accessory buildings, basement exceptions, tall retaining walls and similar items. Heritage trees on the lot and near its edges drive much of the plan: a certified arborist’s inventory, a tree protection plan reviewed by the Town Arborist, and protection fencing inspected before the permit is issued. Grading and drainage, the fire district and a construction operations plan add their own steps. (we confirm per lot)

1. Who reviews what

A small town with detailed rules and several outside agencies

Atherton is a small town in San Mateo County. The Town’s Planning and Building departments share the Permit Center, and the Town Arborist works alongside them. Fire review comes from the Menlo Park Fire Protection District, and gas, electric, water and sewer service come from outside providers rather than the Town.

Town office or agencyWhat it covers on a house project
Planning DepartmentZoning clearance inside the building permit, plus the discretionary applications: special structures permits, variances, heritage tree requests that go to the Planning Commission, lot line changes and historic questions.
Building DepartmentPlan check, building, demolition and grading permits, the Construction, Operations and Parking (COP) plan, construction time limits and inspections.
Town ArboristHeritage trees: tree protection plans, protection zones, exception requests, removal applications, landscape screening review and the arborist reports filed during construction.
Public Works and the City EngineerGrading and drainage plans, stormwater detention, basement drainage and groundwater rules, and encroachment permits for driveway approaches, utility connections and tree work in the street.
Planning Commission and City CouncilThe Commission hears special structures permits, variances and contested heritage tree removals at public meetings; its decisions can be appealed to the City Council.
Menlo Park Fire Protection DistrictFire review of site access, gates, additions and alterations, fire sprinkler plans and generators; a copy of its approval letter goes to the Town with the building permit package.
Outside utilities and agenciesPG&E for gas and electric, California Water Service for water, one of the Town’s two sewer districts, the regional air district for demolition, and the school district.

Summarized from Town of Atherton Building, Planning, Arborist Services, Public Works and Planning Commission pages, the Atherton Municipal Code and the Menlo Park Fire Protection District plan submittal page, read November 1, 2026.

Two checks come first. The lot has to be inside Town limits: some addresses with an Atherton mailing address can sit in unincorporated San Mateo County or a neighboring city, with a different permit office. And the Town’s eTRAKiT property lookup shows the zoning and General Plan designation, the Assessor lot size and the FEMA flood designation for a parcel, along with past permits and planning files. Sewer service is split between two districts depending on the street, which the Town’s sewer page maps out. (we confirm per lot) Our Atherton page describes the kind of homes we take on in Town.

2. Zoning clearance and when the Planning Commission is involved

Most homes are checked at staff level; some items go to a hearing

Under the Town’s zoning clearance chapter, every structure that needs a building permit needs zoning clearance, and it is handled as part of plan check rather than on a separate application. The town planner can ask for plan changes or attach conditions, and the building permit can’t be issued without it. In practice, that means a new house designed squarely within the standards moves straight into the building permit. The Planning forms and handouts page notes that some owners still choose to get Planning’s sign-off on the site plan, floor plans and elevations before the engineering and full construction drawings are finished, which can make sense on a complex lot.

Type of approvalWhen it comes up on a houseWho decides
Zoning clearanceEvery project that needs a building permit. There is no separate form; the town planner checks the plans against the zoning code during plan check and can require changes or add conditions.Town planner, inside the building permit
Special structures permitTaller main buildings in R-1A, accessory buildings in the cases the code lists, basement exceptions beyond the first-floor footprint, basements under accessory buildings with light wells, taller or closely spaced retaining walls, and some additions to nonconforming houses in R-1B.Planning Commission, at a public meeting
VarianceA request to depart from a development standard because of something unusual about the lot.Planning Commission
Heritage tree removal or protection zone exceptionRemoving a healthy heritage tree, or building, trenching or paving inside its protection zone.Town Arborist for dead or dangerous trees and staff-level zone exemptions; the Planning Commission for other removals and zone exceptions
Historic resource evaluationExterior changes to, or demolition of, an older building, when staff ask for one after reviewing the photos and the Town’s records.Planning staff

Simplified from the Atherton Municipal Code zoning clearance and special structures chapters, the heritage tree ordinance and the Universal Planning Application, read November 1, 2026.

Discretionary applications use the Town’s Universal Planning Application. Under the special structures permit chapter, the Commission has to find that the structure won’t harm neighbors’ privacy or views, that it meets the other standards such as height and landscape screening, and that it fits the General Plan. The Planning Commission usually meets monthly, and its members often visit the site before deciding. The application wants a project narrative addressing the findings, a recent topographic survey that extends onto the neighboring lots, context photos, plans and sections measured from average natural grade, a landscape plan and, where heritage trees are near the work, an arborist report and tree inventory.

3. R-1A and R-1B standards

Floor area, height, setbacks and the main building area

The Town has two residential districts, R-1A and R-1B. R-1A covers the larger estate lots and carries deeper front and rear yards and a taller height limit; R-1B covers smaller lots with tighter setbacks and a lower height limit. The standards that shape most Atherton houses:

  • Floor area: the maximum floor area is tied to lot size, with a formula for lots under an acre. In R-1A, floor area above the first floor is capped at a smaller share of the lot, which keeps upper floors modest relative to the footprint. Open trellises and some roofed areas open on two or more sides are excluded within limits.
  • Height and sidewalls: both districts limit overall height and, separately, the height of vertical sidewalls and columns, measured from average natural grade. Dormers above the sidewall line are limited in total length and must sit below the ridge. In R-1A, a taller main building is possible with a special structures permit and setbacks increased in proportion to the extra height.
  • Setbacks and the main building area: the front, rear and side yards define the main buildable area. That line matters beyond the house itself, since many trees outside it qualify as heritage trees, and basement limits, accessory structures and screening all key off it.
  • Hetch Hetchy frontage: on R-1A lots next to the San Francisco water system’s Hetch Hetchy right-of-way, where the neighbor kept surface rights, setbacks can be measured to the original line rather than the edge of the strip.
  • Accessory structures: total accessory building area is capped relative to lot size, separate from pools, sport courts and driveways, and some accessory buildings need a special structures permit.
  • Noise and lighting: mechanical equipment has to meet the Town’s noise rules, and planning applications can ask for an exterior lighting plan.

The Planning FAQ is direct about it: what can be built depends on the zone, lot size, lot shape and existing square footage, and the Town recommends meeting a planner before submitting plans. Planning counter hours, listed on the Planning Department page, are limited to a couple of days a week, with other times by appointment, so we book that meeting early.

4. Heritage trees

The rule that shapes most Atherton site plans

The Town’s heritage tree ordinance protects heritage trees, and the definition is broad. It covers native oaks (valley oak, coast live oak and blue oak) above a set trunk size anywhere on a lot; any other tree above the same size outside the main buildable area, including split-trunk and multi-stemmed trees measured by the Town’s method; and trees the City Council designates. A short list of disfavored species, including eucalyptus, several acacias, tree of heaven and mimosa, is excluded and can’t be used as replacement trees. Heritage trees on a neighbor’s lot near the shared line, and street trees in front of the property, count too.

The Town’s Arborist Services and Tree Protection page, its tree protection plan review requirements and the Heritage Tree Preservation Standards and Specifications lay out what a development project needs:

  • Tree inventory and appraisal by the owner’s certified project arborist, covering every heritage tree on the site and near the property lines: species, size, protection zone, condition, prognosis, photo and appraised value.
  • A separate tree protection plan sheet at a large scale, showing each tree, its protection zone, the fencing, and every utility trench, hardscape area and spot where hand digging is proposed. Significant root cutting needs a project arborist letter with mitigation and Town Arborist approval before work starts.
  • Neighbor notice: where the plan includes heritage trees on a neighboring lot near the line, the applicant sends that owner a courtesy notice by certified mail and gives the Town proof of it.
  • Protection in the field: chain link fencing on driven posts at the protection zone, Town warning signs and a mulch layer under the dripline, installed and inspected before the building permit is issued and left in place until construction is complete. Any change needs a revised plan approved by the Town Arborist.
  • Reports during construction: the project arborist files quarterly inspection reports with the Town throughout construction.
  • Exceptions and removals: work inside a protection zone needs a protection zone exemption or exception, reviewed by the Town Arborist or, in some cases, the Planning Commission. A dead or dangerous heritage tree can be approved for removal by staff; removing a healthy one goes to the Planning Commission, which weighs factors such as the tree’s condition, safety, its value to the area, and whether reasonable use of the property is possible without removing it. Approved removals come with replacement planting, larger replacement oaks where an oak in the buildable area is removed, and a maintenance agreement backed by a bond.

The ordinance makes the property owner responsible for violations, including damage done by contractors, gardeners and other workers on the property. On a typical Atherton lot, a large oak near the middle of the site, or a row of trees along a side line, can decide where the house, driveway, pool and utility runs go. That is why we get the arborist and surveyor out before the architect commits to a footprint.

5. Landscape screening and site details

Privacy planting the Town checks before final

Atherton’s landscape screening rules aim to soften the impact of new structures on neighbors and keep a reasonable degree of privacy between homes. According to the Town’s landscape screening checklist, a landscape screening permit is required for new construction above a set height, and for additions or accessory structures above a lower height when they sit within set distances of a property line. When it applies, screening is required along the side and rear yards and along front yards that don’t face a street.

  • New trees are planted at a minimum box size, with larger or smaller stock at the discretion of the Building Official or Town Arborist, and the planting has to screen the structure within a set number of years.
  • The screening plan shows existing trees and shrubs used for credit, new plantings with species and container sizes, automatic irrigation and heritage tree protection measures, and screening has to be kept well away from heritage tree trunks under the Town’s tree standards.
  • The Town Arborist visits the site during review and inspects the planting after the screening permit is issued. The screening plan can be deferred to framing, but the planting has to be installed and approved before final inspection and occupancy.

Fences, walls and gates have their own guidelines on the Town’s general building information handouts, and street-frontage landscaping, driveway approaches and any work in the street follow the Public Works standards on the encroachment permits page. New landscapes also follow the state water-efficient landscape rules the Town has adopted, with a plan that can be deferred until landscape installation. Our landscape company, Paso Robles Landscaping, plans screening, irrigation and hardscape around these requirements.

6. Basements, drainage and groundwater

What the Town allows below grade and how water is handled

Basement limits. Many Atherton homes include a basement, and the basement chapter sets clear limits. A basement under the main building is limited to the footprint and floor area of the first floor, with small extensions approvable at staff level and larger squared-off extensions only by special structures permit within the code’s parameters. Basements under accessory buildings are allowed only as nonhabitable space without light wells unless the Commission grants a special structures permit, with a finding that heritage trees won’t be affected. A garage can go in a basement under a building within the main building area, and on hillside lots, basement floor area exemptions also run through a special structures permit.

Drainage and stormwater. Grading and drainage is a separate submittal to Public Works, prepared by a civil engineer under the Town’s drainage criteria and the checklist on the Public Works construction and engineering page. The plans have to show that the project doesn’t block surface or subsurface flow across the property, and the Town requires stormwater detention, to reduce peak flows to downstream creeks and channels, on projects that create or replace more than a set area of impervious surface. A single-family home that creates or replaces a significant area of impervious surface also has to include site design measures such as directing roof runoff to cisterns or planted areas, or using permeable paving for walks, patios and driveways. The arborist report is submitted alongside the storm drain report, and before final the engineer of record certifies that the work matches the plans.

Groundwater. Any excavation has to report the depth to groundwater. East of Alameda de las Pulgas, the Town’s groundwater map or a site geotechnical investigation can be used; west of it, a site geotechnical investigation is required. Basements may not impede groundwater flow, so they are wrapped with a subdrain system and protected against releasing construction materials into the groundwater. Pumping groundwater to the Town’s storm drains is only accepted for a short period during construction, after which water has to go to injection wells or another approved method, and permanent groundwater pumping after construction isn’t allowed. Basement entries, windows and vents must be protected above the local flood water level, the structure has to be designed for buoyancy, and light wells need their own storage and pumping. The building submittal also has to include waterproofing plans when a basement is proposed.

A basement in Atherton is very buildable, but the soils report, groundwater level, shoring and waterproofing need to be in the first budget, not discovered after excavation starts.

7. Teardowns and demolition

How an existing house comes down

Many Atherton projects start by removing an existing house. The Town’s demolition permit checklist explains that a demolition permit is required for any complete demolition and may be required for a large partial demolition. The application includes the building permit application, a construction and demolition recycling calculation, and a COP plan with tree protection showing every structure to be removed. By ordinance there is a minimum waiting period between submittal and permit issuance, and during it the owner obtains:

  • the regional air district’s demolition approval number;
  • letters confirming that gas, electric and sewer service have been terminated, with gas cut off at the main or street unless a protection plan is approved;
  • for a pool, the sewer district’s permit to drain it or lab documentation that the water has been treated.

Before the permit is issued, the Town Arborist visits the site to check the COP plan and tree protection, and a building inspector makes a pre-demolition inspection to confirm general demolition requirements and that construction fencing screens the site from the street. Older homes can also carry asbestos-cement siding or roofing and other hazardous materials; the Town publishes a handout on asbestos-cement materials and a PCB screening assessment form.

Historic review. The Universal Planning Application asks for photos of every exterior of a building of a certain age when the project changes its exterior or removes it. After reviewing those and the Town’s Heritage Room records, staff may ask for a Historic Resource Evaluation, which is worth building into the schedule on an older house. Older houses also hide structural and systems surprises; our guide to remodeling an older home walks through the usual ones.

8. Fire district review

Access, gates and sprinklers

Fire review in Atherton comes from the Menlo Park Fire Protection District, not the Town. Its Menlo Park Fire Protection District plan submittal page lists the residential plans it reviews: site and access plans with hydrant location, driveway length and width, fire flow from the water provider and the distance from the house to the property lines; gates, which need a key override switch for fire access; additions and alterations; fire sprinkler and fire protection plans; and generators and propane tanks. Plans are submitted through the District’s online permit portal, the owner signs or authorizes the submittal, and a copy of the District’s approval letter goes to the Town’s Building Department with the building permit package.

The District’s local amendments to the fire code for Atherton require fire sprinklers in new buildings above a small size and in every building with a basement, and they don’t allow partial systems that protect only part of a building. Existing homes can also be required to add sprinklers when a remodel or addition is large enough, which is worth knowing before scoping a major remodel.

Atherton’s planning application asks whether any part of a property is in a very high fire hazard severity zone; an address can be checked on the State Fire Marshal’s fire hazard severity zone maps. A mapped lot brings in the state’s wildfire construction rules for roofs, vents, siding and decks, which our fire hazard severity zone guide explains. On sloped lots, our hillside lot guide covers grading, retaining and foundations.

9. The building permit

What goes into the package and what the Town checks

The Town’s Building Department page and permit applications and forms page lay out the starting documents, and the building plan submittal checklist lists what a full set has to include; checklists for demolition, grading and drainage, pools, generators and wells are on the submittal checklists page. Plans are uploaded to the Building ePlan submittal portal, and an incomplete set can be returned without review. A new house package typically includes:

  • the building permit application and the Town’s square footage worksheet, with actual structure areas alongside the planning floor area figures;
  • a cover sheet with design criteria, special inspections, deferred submittals, a sheet index and whether the house will be sprinklered;
  • a site plan with setbacks and trees, the Construction, Operations and Parking (COP) plan, the tree protection plan and, for remodels, a demolition plan;
  • architectural, structural, electrical, mechanical and plumbing plans, building sections and window schedules coordinated with the energy forms;
  • a geotechnical report with the geotechnical engineer’s letter confirming the plans follow its recommendations, waterproofing plans for any basement, Title 24 energy calculations and CALGreen mandatory measures, and a special inspection agreement.

Grading permits, landscape screening and water-efficient landscape plans are separate submittals; the last two can be deferred. Other agencies sign off too: the fire district approval letter, school district notification and, for a teardown, the air district approval number. The primary contractor needs a Town business license before the permit is issued, and a subcontractor list showing every subcontractor’s Town license is required before final.

Energy. The state’s 2025 Energy Code governs projects whose permit applications are filed on or after January 1, 2026. A few of the Town’s posted handouts still cite older code editions, so we check which codes and local amendments the Building Department is enforcing at submittal. Heat pumps, solar and insulation choices under that code are covered in our Title 24 overview.

10. Construction rules

Hours, the COP plan and time limits

Atherton regulates how a job runs as closely as how it is designed. Under the Town’s construction regulations and its Construction, Operations and Parking plan guidelines, the COP plan, which becomes part of the public file, has to show:

  • a rocked construction parking area outside tree protection zones and large enough for the crew, with any street parking limited to the frontage directly in front of the site, on the same side of the street;
  • a rocked temporary construction driveway extending into the property to limit mud and dust;
  • the debris box, construction trailer and sanitary facilities on private property, set back from the property lines and kept out of neighbors’ views where possible;
  • a signed cleanup area away from tree canopies and planting areas, and materials storage outside tree driplines.

Construction, deliveries and servicing are limited to weekday daytime hours, with no work of any kind on weekends or Town holidays, as the Town’s construction hours and inspection page sets out; the Town offices also close for the entire holiday week at the end of December, through New Year’s Day. Inspections are requested by phone a day ahead, and someone has to be on site with the approved plans and job card.

Atherton also puts a time limit on construction. The time limits handout explains that each project has a completion deadline scaled to its size, counted from the date the building permit is issued, with final inspection marking completion. Calling for inspections keeps a permit active but does not extend that deadline, and the property owner faces daily penalties that increase the longer a project runs past it. A realistic schedule, agreed before the permit is pulled, is part of the contract on every Atherton job. The Building Department also hosts a regular Builders’ Roundtable for contractors working in Town.

11. Remodels and additions

What changes when you work with the existing house

Work on an existing Atherton house runs through the same departments, but several rules only come up when part of the old structure stays:

  • Nonconforming houses: under the nonconforming buildings chapter, a house that was legal when built but no longer meets today’s setbacks or height can be altered or added to as long as only a limited share of its floor area and nonconforming walls are rebuilt, in one project or cumulatively over a few years. Beyond that, the whole house has to meet current zoning and building codes.
  • R-1A and R-1B differences: in R-1A, an addition can keep the existing setback lines within limits and the existing height up to the standard limit; in R-1B, additions to a nonconforming house have to stay within the main building area unless the Commission grants a special structures permit.
  • Alteration or demolition: when a project is filed as an alteration rather than a demolition, Planning may limit how much of the existing exterior walls and elevations can be removed and ask for supporting calculations, so the plans need to show which walls stay.
  • Trees: new foundations, trenches and patios near a heritage tree need the same tree protection plan, arborist review and fencing as a new house.
  • Fire sprinklers: a large enough remodel or addition can trigger sprinklers for the whole house under the fire district’s rules.
  • Kitchens and baths: the Town posts separate kitchen and bathroom remodel handouts and a list of work exempt from permits on its general building information page.

For how we scope and manage this kind of work, see our whole-home remodels and home additions pages.

12. Order of steps

How we usually sequence an Atherton project

StageWhat it involvesWhat tends to drive timing
Address, zoning and recordsConfirm the lot is inside the Town, pull the zoning district, lot size and flood designation from eTRAKiT, and review past permits and planning files.Quick once the address is known.
Survey and tree inventoryTopographic and boundary survey reaching onto the neighboring lots, and a certified arborist’s inventory and appraisal of every heritage tree on the site and near the property lines.Surveyor and arborist calendars.
Planner meetingFloor area, height, setbacks, the main building area, basement limits and whether any Planning Commission approval is needed.Counter days and appointments.
Planning Commission, if neededSpecial structures permit, variance or heritage tree request, with a public meeting, a field visit by commissioners and a possible appeal.The monthly meeting calendar.
Building permit packagePlans, square footage worksheet, COP plan, tree protection plan, geotechnical report, Title 24 and CALGreen documents, filed on the ePlan portal; grading and drainage filed with Public Works; fire plans to the fire district.Correction rounds across departments.
Demolition, if a teardownDemolition permit with its waiting period, air district approval, utility disconnection letters, Town Arborist visit and a pre-demolition inspection.Air district and utility timing.
Tree protection and site setupProtection fencing and signs installed and inspected before the building permit is issued; rocked construction parking, driveway and debris box placed per the COP plan.Arborist sign-off.
Construction and finalInspections booked through the Town’s inspection line, quarterly arborist reports, and the sign-offs for landscape screening, grading and drainage, encroachment work, fire and the subcontractor list before final.Construction, and the Town’s time limit on the permit.

A typical Atherton sequence; lot size, trees and a basement can each change it.

Our custom home timeline guide puts design, approvals and construction on one calendar, and our owner-builder vs licensed contractor guide is worth reading for anyone thinking about running the job themselves. Neighboring cities work differently: Palo Alto uses Individual Review for second stories, and Los Gatos and Saratoga have their own hillside and design rules, covered in our Palo Alto permit guide, Los Gatos permit guide and Saratoga design review guide.

13. Before you design

Questions to answer about your Atherton property

  1. Is the address inside the Town of Atherton, or in unincorporated San Mateo County or a neighboring city?
  2. Is the lot zoned R-1A or R-1B, and where does the main building area fall after setbacks?
  3. How much floor area does the lot allow, and how much of it can go above the first floor?
  4. Does the design need a special structures permit or variance, and does that add a Planning Commission meeting?
  5. Which heritage trees are on the lot, on the neighbors’ lots near the line and in the street, and where are their protection zones?
  6. Will the house, driveway, pool or utility trenches need a protection zone exception or a tree removal request?
  7. Which new walls trigger landscape screening, and where will the screening go?
  8. For a basement, what does the geotechnical report say about groundwater, and does the plan stay within the first-floor footprint?
  9. How will stormwater detention and the site design measures fit the landscape plan?
  10. For a teardown, how will air district approval, utility disconnection and the demolition waiting period fit the schedule?
  11. Where will construction parking, the debris box and materials storage go without touching a tree protection zone?
  12. Does the construction schedule fit inside the Town’s time limit for a project of this size?

Owners who already have an architect send us the drawings and we estimate and build from them; owners starting from scratch can have Harrod Drafting & Design, our sister studio, draw the house or addition and the permit set.

How we help

What Harrod Built brings to an Atherton project

Harrod Built (CSLB #986950) is a family-run general contractor working on the Peninsula, in the South Bay and on the Central Coast. On an Atherton job, our part usually looks like this:

  • Due diligence up front. We map zoning, the main building area, floor area, heritage trees, basement limits, drainage and site logistics, then write an estimate around those constraints.
  • Trees planned first. Surveyor and project arborist out early, so the footprint, driveway, utility runs and construction parking respect every protection zone before the plans are drawn.
  • Costing revisions early. If the town planner, the Town Arborist or the Planning Commission asks for a change, we put a number on it before the drawings are revised, so the owner can weigh it.
  • Basements planned properly. Groundwater, shoring, subdrains, waterproofing and the dewatering method worked out with the geotechnical and civil engineers before excavation.
  • Teardown sequencing. Air district approval, utility disconnection letters, the demolition waiting period and the pre-demolition inspection lined up so demolition can start as soon as it is allowed.
  • A schedule that fits the Town’s time limit. A realistic construction schedule agreed before the permit is pulled, with weekday-only work and holiday closures built in.
  • Design support. Harrod Drafting & Design can draw the house and permit set, or we work from the plans of the architect you have already hired.
  • Screening and gardens. Paso Robles Landscaping, our landscape company, handles screening plantings, irrigation and permeable hardscape laid out around the protection zones.
  • On site. Our project manager and site lead hold the job to the COP plan, keep fencing and erosion control intact, coordinate the arborist’s quarterly reports, book inspections and keep the owner informed week to week.

Before hiring any builder, look the license up on the state license lookup; the CSLB’s tips for hiring a contractor and our article on how to check a CSLB license explain what to look for. Nearby we also work in Palo Alto, Woodside and Portola Valley, Los Gatos and Saratoga as well as Atherton, and farther south in Monterey, San Luis Obispo and Santa Barbara counties, through general contracting or design-build. our process page shows the steps from estimate to move-in, and our guide to choosing a contract type compares fixed-sum and cost-plus agreements. For the local market, read our page on building a high-end home in Atherton.

Weighing a lot, a rebuild or a plan set in Atherton? Share the address and any drawings you have. We look at zoning, heritage trees, basement and drainage questions and site logistics, then send a written estimate. Phone 805-712-8993 or reach us here.

Sources: Town of Atherton Building Department pages (Building, Permit Applications and Forms, Submittal Checklist, General Building Information, Construction Hours and Inspection Information, Building ePlan Submittal, eTRAKiT Web Portal, Business Licenses, Building FAQs); Building plan submittal checklist, demolition permit checklist, Construction, Operations and Parking plan guidelines and time limits handout; Arborist Services and Tree Protection page, tree protection plan review requirements, Building Submittals and Heritage Trees sheet, Heritage Tree Preservation Standards and Specifications, and landscape screening checklist. Planning Department page, Forms and Handouts, Planning FAQs, Universal Planning Application and Planning Commission page. Public Works construction and engineering page, drainage criteria, encroachment permits page, and the sewer and water utility pages. Atherton Municipal Code: zoning clearance, special structures permit, R-1A and R-1B development standards, nonconforming buildings, basements, heritage tree ordinance and construction regulations. Menlo Park Fire Protection District plan submittal page and its local fire code amendments for the Town. State sources: OSFM fire hazard severity zone maps, the CEC’s 2025 energy standards and the CSLB, all reviewed November 1, 2026. Treat this page as an overview rather than legal or code advice; the rules that apply to a specific lot are whatever the Town of Atherton and the other agencies decide.

FAQ

Common questions

Something else on your mind? Call Michael at 805.712.8993.

Who issues building permits in Atherton?

The Town of Atherton Building Department issues building, demolition and grading permits for homes inside Town limits, with plans submitted through the Town’s ePlan portal. Planning reviews zoning as part of the building permit, the Town Arborist reviews tree protection, Public Works reviews grading and drainage, and the Menlo Park Fire Protection District reviews fire items.

Does Atherton have design review for a new house?

The Town doesn’t run a separate design review board for a single-family home that meets the code. The town planner checks the plans against the zoning standards through zoning clearance inside the building permit. A Planning Commission hearing comes in when the project needs a special structures permit, a variance or a contested heritage tree removal.

What is a heritage tree in Atherton?

Native valley, coast live and blue oaks above a set trunk size anywhere on a lot, any other tree above the same size outside the main buildable area, and trees designated by the City Council. A few disfavored species such as eucalyptus and some acacias are excluded. Heritage trees on neighboring lots near the property line and street trees in front of the lot are covered too.

When is a special structures permit required in Atherton?

For taller main buildings in R-1A, certain accessory buildings, basement extensions beyond the first-floor footprint, habitable basements with light wells under accessory buildings, taller or closely spaced retaining walls, and some additions to nonconforming houses in R-1B. The Planning Commission decides at a public meeting, based on privacy and view impacts on neighbors and the other standards.

Can I build a basement in Atherton?

Yes, within limits. A basement under the main house is generally kept to the footprint and floor area of the first floor, with larger exceptions only by special structures permit. The Town’s drainage criteria require a groundwater check, subdrains that keep groundwater moving, only short-term construction pumping, flood protection at basement openings and a design that resists buoyancy, and the fire district requires sprinklers in a building with a basement.

What construction rules apply to a job in Atherton?

Work and deliveries are limited to weekday daytime hours, with no work on weekends or Town holidays. Every job needs an approved Construction, Operations and Parking plan with on-site parking and storage outside tree protection zones, and each building permit carries a completion time limit scaled to the project’s size, with penalties to the owner if it runs over.

Planning guides

Budget and planning guides

Start your project

Planning a home, remodel or addition in Atherton? Tell us about your property.

A few details help us call you back with useful answers about budget, schedule and permits.