Planning guide · updated October 2026
A kitchen remodel runs on two clocks. The first one starts at the walk-through and covers design, selections, ordering and, for most kitchens, a permit. The second starts the day the old cabinets come out. Most of the frustration people hear about comes from starting the second clock before the first one is finished. This guide walks through what happens in each phase, in the order it usually happens, and what tends to speed it up or slow it down. Questions about your own kitchen? Call 805-712-8993.

The short answer
A kitchen remodel moves through the same phases almost every time: walk-through and scope, design, selections and ordering, the permit, then demolition, rough-in, rough inspections, walls and floors, cabinets, countertops, finishes, and a final inspection with a punch list. On our own jobs, construction on a kitchen typically runs about four to eight weeks once work starts, depending on scope; a new layout, a moved wall or late selections push it longer. The planning phases come first, and finishing them before demolition is the single biggest thing that keeps the construction weeks on track. Call 805-712-8993.
1. The whole picture
Every phase, in order
Here is the sequence we follow on the kitchens we remodel, with the part of each phase that usually decides how long it takes. Not every kitchen needs every row. A refresh that keeps the sink, range and walls where they are can skip the engineering and move through rough-in quickly. A kitchen that opens into the family room touches nearly every row, and some phases overlap.
| Phase | What happens | What usually sets the pace |
|---|---|---|
| Walk-through and scope | We measure the room, open the sink base, look at the panel, the plumbing and the floor, and talk through how you use the kitchen. | How quickly you settle on a direction: same layout with new finishes, or a new layout. |
| Design and drawings | A layout, cabinet drawings and, for bigger changes, permit drawings and engineering for any wall or beam that moves. | Whether a load-bearing wall comes out, and how many rounds of revisions the layout takes. |
| Selections and ordering | Cabinets, appliances, sink and faucet, counter material, tile, lighting and hardware are chosen and ordered. | Lead times on cabinets and special-order items, and decisions that are still open. |
| Permit | If the work alters plumbing, electrical, mechanical or structure, the building department reviews it and issues a permit. | The size of the project, the department’s review path, and how quickly corrections are answered. |
| Protection and demolition | Floors and the rest of the house are covered, a temporary kitchen is set up, and the old kitchen comes out. | What turns up behind the cabinets and under the floor. |
| Rough-in | Framing changes, new plumbing and gas lines, new circuits and boxes, the hood duct, and blocking for cabinets. | How much of the layout moves, and how old the existing systems are. |
| Rough inspections | The inspector checks the work before walls and ceilings are closed. | Scheduling, and whether any corrections are needed before a re-inspection. |
| Walls, ceiling and floor | Insulation where walls were opened, drywall, finish and paint, and flooring in the sequence the floor material needs. | Drying time, and the order the flooring and cabinets need to go in. |
| Cabinets | Boxes are set, leveled and fastened, then panels, fillers and trim. | Whether every cabinet arrived, and arrived undamaged. |
| Countertops | The fabricator templates the installed base cabinets, fabricates the tops, then installs them. | The fabricator’s schedule and the counter material. |
| Finishes and fixtures | Backsplash, plumbing fixtures, lights, outlets, appliances and hardware. | Any item that is late or the wrong size. |
| Final inspection and punch list | The building department signs off, and we walk the kitchen with you and finish the small items. | Final inspection scheduling, and back-ordered parts. |
The usual order of work on the kitchens we remodel. Every kitchen is different; some phases overlap and some are skipped on a refresh that keeps the layout.
The first four rows happen before anyone picks up a pry bar, and on a kitchen with a new layout they can take as long as the construction itself. That is normal. A schedule only holds once the drawings, the selections and the permit are settled. If you are planning a new home rather than a remodel, our guide to how long a custom home takes covers the same idea at a larger scale.
2. Before construction
Design, selections and the contract
Scope comes first
The first decision is how much of the kitchen changes. Keeping the sink, range and refrigerator where they are keeps the plumbing, gas and electrical work simple. Moving them, adding an island with a sink, or taking out a wall turns a finish project into a construction project, with drawings, possibly engineering and a longer permit review.
For a new layout, drawings come next. Our design studio, Harrod Drafting & Design, draws remodel layouts and permit sets; if a wall that carries the roof or a floor above is coming out, a structural engineer sizes the beam and the posts that hold it.
Selections decide the schedule
Cabinets are usually the item that sets the start date. Semi-custom and custom cabinets are built to order, so the order has to be placed early, and the cabinet drawings cannot be finished until the appliances are chosen, because the openings are sized to the exact models. The sink and faucet need to be picked before the countertop fabricator templates, and lighting needs to be chosen before the electrician roughs in boxes. Our rule of thumb: the more that is decided before demolition, the shorter the time your kitchen is out of service.
The contract sets the dates
California law spells out what a home improvement contract must say. Under section 7159 in the 2026 CSLB Law Book, it needs an approximate start date, a statement of what counts as substantial commencement of work, and an approximate completion date. If payments are due before the job is finished, the contract needs a schedule of progress payments that describes each phase of work and what is supplied in it, and the law prohibits a contractor from collecting payment for work not yet completed or materials not yet delivered, with limited exceptions for contractors who furnish certain bonds (section 7159.5 also caps the down payment). CSLB’s home improvement contract basics adds that the contract should say who will get the permits, and its homeowner contract checklist asks whether the contract tells you when work will start and end.
Two more dates matter. Many home improvement contracts come with a three-day right to cancel, and homeowners 65 and older get five days; CSLB’s cancellation and lien notice rules explain when it applies. And the contract will include a notice about mechanics liens, which is worth reading before the first payment. Our guide to fixed price and cost-plus contracts covers how different contract types handle allowances and changes.
3. The permit
Does a kitchen remodel need one, and how long does that take?
Usually, yes. Swapping a faucet or painting cabinets does not need a permit. Moving plumbing, adding circuits, changing a gas line, adding a vent or taking out a wall almost always does.
Unincorporated San Luis Obispo County
- When a permit is needed. The County’s construction permit FAQ says a construction permit is needed for almost any project that involves building or altering a structure or its plumbing, mechanical or electrical systems.
- Small items can be quick. The County’s Express Permits let licensed contractors apply online for small repairs and installs, such as lighting, an electrical panel replacement or a water heater, in certain residential zones. The FAQ notes that some small permits, such as electrical permits, can be issued over the counter the same day when the submittal is complete and the fees are paid.
- Bigger changes go through plan review. A kitchen with structural changes or a new layout is reviewed against the plans before the permit is issued, and the County is clear that no work should be done until the permit is actually issued. Our guide to what needs a permit for a remodel in SLO County goes through other projects item by item.
- Applications do not wait forever. The FAQ also notes that a permit application expires if the permit is not issued within the County’s time limit, so answering plan check comments promptly matters. The Building & Construction page links the full process.
Cities have their own departments
Inside city limits, the city’s building department issues the permit. In Paso Robles, the Building Division takes all submittals electronically through its online portal and asks owners who are unsure whether a project needs a permit to email or call. Other cities, including San Luis Obispo, Atascadero and Arroyo Grande, run their own counters, and Monterey and Santa Barbara counties have their own processes. Our city vs County permit guide explains which office covers which address.
The energy code touches the lighting
California’s 2025 Energy Code applies to altered and newly installed lighting in a remodel. The Energy Commission’s compliance manual chapter on additions and alterations gives a kitchen example: when a new fixture is added over the sink, the new and altered fixtures must meet the luminaire efficacy rules, and newly installed recessed downlights cannot use screw-base sockets. Existing lighting that is not being altered does not have to be replaced. Our Title 24 guide covers the rest of the code.
4. On site, week by week
What happens once construction starts
Here is how the construction weeks usually unfold on a kitchen that gets new cabinets, counters, flooring and lighting, with the plumbing and gas staying close to where they are. A bigger layout change adds time inside the same sequence rather than changing it.
First week: protection, temporary kitchen and demolition
Before anything comes out, we protect the floors and walls along the path to the kitchen, seal off the work area to keep dust out of the rest of the house, and help set up a temporary kitchen somewhere else in the home. Then the old cabinets, counters, appliances and, if it is being replaced, the flooring come out. Water, gas and power to the room are shut off and capped.
Older houses need a check first. If the home was built before 1978, the EPA’s Renovation, Repair and Painting rule requires that anyone paid to disturb painted surfaces be certified and use lead-safe work practices. Asbestos has no similar cut-off date; the San Luis Obispo County Air Pollution Control District explains when a survey by a certified asbestos consultant is required before a renovation and when notification applies. Testing suspect materials, such as old flooring, ceiling texture or drywall compound, during the design phase keeps demolition from stopping for results.
Demolition is also when the house tells you its secrets: water damage under the sink or dishwasher, rot in the subfloor, old wiring, undersized circuits, galvanized pipe or earlier work that was never permitted. We look for clues on the walk-through, but some things only show up when the cabinets are gone.
Next: framing and rough-in
Any framing changes come first: a new opening, a soffit removed, a beam set in place of a wall. Then the trades rough in: the plumber runs supply and drain lines to the new sink, dishwasher and refrigerator locations; the gas line goes to the range if it is gas; the electrician adds circuits and boxes for appliances, lighting and outlets; and the hood duct is routed to the outside. The carpenter adds blocking in the walls so upper cabinets and shelves have something solid to hang on.
Then: rough inspections
Before any of that is covered, it has to be inspected. In the unincorporated County, the building inspections page says every portion of a project that needs a permit must be inspected before the work is covered or concealed. The permit comes with an inspection card listing each inspection, and some, such as pressure tests on gas or water lines, require a test the inspector watches. Requests go in through the County’s online portal by the afternoon cutoff the day before, and the contractor is given a two-hour window. In Paso Robles, the city’s inspection request page sets its own cutoff the day before. If something does not pass, the inspector leaves a correction notice, and a re-inspection follows once it is fixed.
Middle of the job: walls, ceiling and floor
Once rough inspections pass, opened exterior walls get insulation, and drywall goes up over the new work. Drywall is hung, taped, finished and textured to match the rest of the house, then primed and painted. Some of this is waiting for coats to dry, which is why it can feel slow from the outside. Flooring goes in either before or after the cabinets, depending on the material and how it needs to meet the cabinet bases; we settle that order in the plan so the floor and the toe kicks finish cleanly.
Cabinets and countertops
The cabinets are set, leveled, shimmed and fastened together and to the wall, and the panels, fillers and trim are fitted. This is the point where the room starts to look like a kitchen again.
Stone and quartz countertops follow their own sequence. The fabricator templates the tops from the installed base cabinets, not from the drawings, so the cabinets have to be in and level first. The sink, faucet and cooktop specifications need to be on hand at templating so the cutouts are right. Fabrication happens at the shop, then the tops are installed. The gap between templating and installation is set by the fabricator’s schedule and the material, so we book it as early as the cabinet install allows.
Final stretch: finishes, fixtures and appliances
After the counters are in, the backsplash tile is set and grouted, the plumber sets the sink, faucet, disposal and dishwasher, the electrician installs fixtures, outlets and switches, and the appliances, hood and hardware go in. Touch-up paint and caulk finish the room.
Last: final inspection and the punch list
When the work is complete, the building department does a final inspection and signs off the permit. We then walk the kitchen with you and make a punch list of anything that needs adjusting, from a door that needs aligning to a missing piece of trim, and finish it. Any back-ordered item gets its own date so it does not hold the rest of the kitchen hostage. Our how our projects run page covers how communication works while a project is underway.
5. What slows a kitchen remodel
The common causes of delay, and how to plan around them
| What slows it down | Why it costs time | How to plan for it |
|---|---|---|
| Selections still open at demolition | The crew can rough in plumbing and electrical only to the fixtures and appliances it knows about. | Choose appliances, sink, faucet and lighting before construction starts. |
| Long-lead items | Custom cabinets, special-order appliances and some tile are made or shipped to order. | Order early, and start demolition only once the long-lead items have a confirmed ship date. |
| Changes once work starts | Moving an outlet is small; moving a sink or a wall can mean new drawings, new parts and another inspection. | Put each change in a written change order that says how it affects the schedule. |
| Hidden conditions | Water damage under the sink, old wiring, undersized circuits or earlier unpermitted work only show up once things are opened. | Expect some discovery in an older house, and decide in advance how surprises will be handled. |
| Structural changes | Removing or shortening a bearing wall needs engineering, a permit review and often a beam. | Settle the layout and the structure before the permit drawings are finished. |
| Inspections and corrections | Covering work before it is inspected is not allowed, so the job waits for the inspection. | Request inspections ahead of the cutoff, and have the work and the paperwork ready. |
| Lead paint or asbestos | Older homes may need testing, certified crews or special handling before demolition. | Test suspect materials during design, not on demolition day. |
| Living at home | Working around a household means daily cleanup, dust control and protected paths. | Plan a temporary kitchen and agree on working hours and access at the start. |
Patterns we see on our own remodels. None of these is unusual; each is easier to handle when it is planned for.
Changes deserve a special note. Under section 7159.6, a change order is enforceable only if it is in writing and states the scope of the change, the amount added to or subtracted from the contract, and the effect on the progress payments or the completion date. That is good practice for both sides: each change shows up with its time cost before the work starts, not after. If a remodel keeps growing until it touches most of the house, it may be time to compare whole-home remodeling vs. new construction.
6. Living through it
Cooking, cleaning and keeping the house running
Most families stay at home during a kitchen remodel. A few things make that easier:
- A temporary kitchen. The old refrigerator, a microwave, an electric kettle or a countertop cooker in another room, and a nearby sink for washing up, such as a laundry tub or a bathroom vanity.
- A clear path. Agree on which door the crew uses, where materials are stored, and which rooms are off limits, so pets and children are kept away from the work.
- Dust and noise. Plastic barriers, covered floors and daily cleanup keep dust contained. Demolition and drywall sanding are the loudest and dustiest days, and they are known in advance.
- Shut-offs. Water or power to parts of the house may be off for short periods during rough-in and fixture installation. We schedule those with you.
- Weekly check-ins. A short weekly look at what is done, what is next and what decisions are coming up keeps surprises small.
Our remodel cost guide talks about how living at home, phasing and temporary kitchens affect the budget as well as the schedule. Similar sequences apply to bathroom remodels and other interior remodeling projects, on a smaller scale.
7. Before demolition
Ten things to settle before the old kitchen comes out
- The layout is final, including the island, the sink and the range.
- Appliances are chosen by model, so the cabinet openings and the electrical and gas rough-in match them.
- Cabinets are ordered and have a confirmed delivery date.
- Sink, faucet, disposal and any filtered water or pot filler are chosen.
- Counter material and edge are chosen, and you know how the fabricator schedules templating.
- Lighting, under-cabinet lights and switch locations are decided.
- Tile, flooring and paint colors are picked, or allowances are set for each.
- The permit is issued, if the work needs one.
- Any lead or asbestos testing for an older home is done.
- The temporary kitchen, crew access and working hours are agreed on.
Hiring the right kind of contractor matters too. CSLB uses a kitchen as its example of which kind of contractor to hire: when a kitchen remodel includes plumbing, electrical and carpentry under one contract, a licensed B General Building contractor fits. Our guide on how to check a contractor’s license shows how to confirm that on the state’s record.
How we help
Kitchens with Harrod Built
- A walk-through first. Harrod Built is a family general contractor based in Paso Robles, CSLB #986950. We start by walking the kitchen with you and looking at what is behind and under it, then give you a written estimate. You can look us up on the CSLB license check before we meet.
- A schedule built on real dates. We order long-lead items early and schedule demolition around confirmed delivery dates, so the kitchen is out of service for as short a time as the scope allows.
- Drawings when you need them. For a new layout, a moved wall or a permit set, our design studio, Harrod Drafting & Design, draws the plans.
- Indoors and out. If the new kitchen opens onto a patio or an outdoor kitchen, our landscape company, Paso Robles Landscaping, handles the outdoor scope.
Learn more on our kitchen remodeling page. We also handle whole-house remodels, additions, general contracting and design-build for custom homes across San Luis Obispo, Monterey and Santa Barbara counties, from Paso Robles, Templeton and Atascadero to San Luis Obispo.
Planning a kitchen remodel? We can walk the kitchen with you, talk through layout and selections, and put together a written estimate with a construction schedule built around real lead times. Call 805-712-8993 or contact us.
Sources: County of San Luis Obispo Department of Planning & Building: construction permit FAQ, building inspections, Express Permits and Building & Construction pages; City of Paso Robles Building Division and building inspection request pages; Contractors State License Board (CSLB): home improvement contract pages (what is a contract, warnings and exceptions, homeowner checklist) and what kind of contractor you need; 2026 CSLB Law Book, Business and Professions Code sections 7159, 7159.5 and 7159.6; U.S. EPA Lead Renovation, Repair and Painting program; San Luis Obispo County Air Pollution Control District asbestos page; California Energy Commission 2025 Energy Code and Single-Family Residential Compliance Manual, additions and alterations chapter. All checked October 18, 2026. This guide is general information, not legal or code advice; your building department has the final word on what a project needs.
How long does a kitchen remodel take?
It comes in two parts. Planning, which covers design, selections, ordering and the permit, comes first and varies the most. On our own jobs, construction on a kitchen typically runs about four to eight weeks once work starts, depending on scope. A new layout, a moved wall, long-lead cabinets or selections made late add time.
What is the order of steps in a kitchen remodel?
Walk-through and scope, design, selections and ordering, and the permit come first. On site, the usual order is protection and demolition, framing and rough-in for plumbing, gas and electrical, rough inspections, insulation and drywall, flooring and cabinets, countertop templating and installation, backsplash, fixtures and appliances, and finally the final inspection and punch list.
Do I need a permit for a kitchen remodel in San Luis Obispo County?
Usually. In the unincorporated County, a construction permit is needed for almost any project that alters a structure or its plumbing, mechanical or electrical systems. Purely cosmetic work, such as painting, may not need one. Inside city limits, such as Paso Robles or San Luis Obispo, the city’s building department decides. We confirm the requirement before work starts.
Can I live at home during a kitchen remodel?
Most families do. A temporary kitchen in another room, a clear path for the crew, dust barriers and daily cleanup make it workable. Demolition and drywall sanding are the hardest days, and they are scheduled in advance, as are any short water or power shut-offs.
What causes kitchen remodel delays?
The most common causes are selections that are still open when demolition starts, cabinets or appliances with long lead times, changes after work begins, hidden conditions such as water damage or old wiring, structural changes that need engineering, and waiting on inspections or corrections. Most of them can be reduced by finishing the planning before the old kitchen comes out.
Planning guides
Budget and planning guides
Remodel cost in Paso Robles and SLO County
The scope, structure and selection choices behind a kitchen, bath or whole-house remodel budget.
How long a custom home takes to build
The new-build version of this guide: lot, design, permits and construction in order.
Adding a second story
Structure, permits and living arrangements when a remodel goes up instead of out.
Garage conversion or a detached ADU?
Two ways to add living space, compared on permits, utilities and disruption.
SLO County building permits: city vs County
Which building department reviews your remodel, and what its plan check looks at.
Title 24 energy code
California’s energy rules, including the lighting and equipment that remodels touch.
How to check a contractor’s license
Reading the state license record before you sign a remodel contract.
Fixed price vs cost-plus contracts
How each contract type handles allowances, changes and the schedule.
Financing your build
Renovation and construction loans, and the paperwork a lender asks for.
How long a bathroom remodel takes
Every step from tear-out to shower glass, with the permits and inspections in between.
Do I need a permit for my remodel?
Kitchens, baths, windows, roofs, decks, fences and water heaters in SLO County, item by item.
Remodeling an older home
Lead paint, asbestos testing, old wiring and pipes, foundations and the code upgrades a permit can bring.
Remodeling a historic home in Pacific Grove
The historic inventory, screenings and assessments, Historic Resources Committee review, coastal and tree rules and permits.
Start your project
Planning a kitchen? Tell us about it.
A few details help us call you back with useful answers about budget, schedule and permits.
805.712.8993michael@harrodbuilt.com
1345 Riverside Ave, Paso Robles, CA 93446
CSLB License #986950